Assessment, design, consent checks, installation and handover. Use this guide to understand what a Chelmsford installer should cover before you compare quotes.
A survey should cover roof condition and structure, orientation and pitch, shading across the year, usable area, the consumer unit and where cables and the inverter would run. Ask what is done remotely and what is checked on site.
02 / DESIGN
Output for your roof, not an average
Ask for the modelled annual generation for your actual roof slopes and the assumptions behind it. Ask how the design changes if a road-facing slope cannot be used.
03 / INSTALLATION
Scaffold, fix, wire, notify
Understand who provides scaffolding, how panels are fixed to your roof type, what electrical work is included and who notifies the electricity network operator and building control.
Permitted development limits to check against the design
Planning Portal guidance for England, updated for rules that took effect on 27 August 2026 with a transition period, sets limits for panels on a house: on a pitched roof they should project no more than 200mm from the slope and not sit above the highest part of the roof (excluding the chimney); on a flat roof equipment may not exceed 600mm above the highest part of the roof; equipment should be sited to minimise the effect on appearance and be removed when no longer needed. Panels are not permitted development on a building in the grounds of a listed building or on a scheduled monument, and in a conservation area they may not be fitted to a wall or roof slope fronting a highway.